The project page: tasks, views and the project menu

Describes Projects 0.34.0.

A project’s page is where its work happens: the task list and its views, the project’s status, and the menu for everything around it, such as members, files and archiving.

Where to find it

Open Projects in the admin sidebar and click a project’s name (/admin/projects/<id>). You see a project if you’re on it, if its visibility is set to everyone, or if you have Administer all projects. What you may change depends on your role on the project; see the guide on members and access.

The project page of Website relaunch in the List view: tasks with their status, dates, assignees, priority and hours, with Add task and Add sub-project The project page of Website relaunch in the List view: tasks with their status, dates, assignees, priority and hours, with Add task and Add sub-project

A project's tasks in the List view.

The header

Next to the project’s name in the page header:

  • The project’s key, such as WEB.
  • How it runs: since … with its start date (when switched on in the project’s header settings), and how far ahead, behind or overdue it is against its plan. A project that hasn’t started shows Start project, or Start now for a scheduled one, which asks for the start date and time. “Defaults to right now; backdate it if work began earlier, or pick a future moment if you’re queueing it up.”
  • A workflow status select (No status when none is set), when the project uses workflow statuses.
  • ⋮, the project menu.

Badges show when the project is Archived or Completed, and an ongoing project with every task done says All caught up.

The project menu

  • Edit: the project’s form.
  • Members: who is on the project and what they may do.
  • Your API key: the API keys of yours that reach this project.
  • Files: the project’s files, when the Files extension is on.
  • Activity: what happened on the project.
  • Set health: your judgment of how the project is going: On track, Some risk or Concerned, with a Note. “Your judgment, not a computed number.” The result shows in a strip above the tasks, with Update to change it.
  • Invoice effort: creates a draft invoice in Billing from the project’s uninvoiced billable time, after asking “Create a draft invoice from all uninvoiced billable time?”. It shows only to the project’s owner (or an administrator) when the Customer billing extension is on for the project. The draft is reviewed and issued in Billing.
  • Move…: put the project under another project, or take a sub-project out.
  • Archive: “It is hidden from the main lists and kept in the database.” An archived project shows Unarchive instead.

Tabs

Across the top are Tasks, one tab per extension that adds one (such as Hours, Events or Whiteboards), Comments for the project’s own thread, All comments when switched on, and History. A project with nothing switched on says Nothing is turned on for this project yet. and links to Manage this project’s modules & features.

Inside Tasks, a second strip switches between List, Board, Timeline and Calendar. Each view shows only while its feature is on. Add task and Add sub-project sit at the right of that strip.

The task list

Each row shows the task’s status chip, its title, its assignees and, depending on the project’s features, the deadline, estimate, progress, logged time and dependencies. Above the list:

  • Active, Done and All filter the rows, each with a count.
  • The sort select: Manual order, Newest first, Recently updated. Dragging rows is only possible in Manual order; otherwise the list says Reordering off.

Clicking the status chip changes the status. A task is Waiting, Can be started, In progress or Done, and the steps are Allow start, Start, Mark done and Reopen. When a task is done and other tasks were waiting for it, a dialog asks whether to start what comes next: the people ticked are notified that it’s their turn, with your comment, and Keep idle leaves a task waiting.

Clicking the deadline chip changes the deadline (Day, Time, Save, Clear). The trace button on a task with dependencies highlights everything before and after it (Waits on, Unlocks); press it again to Stop tracing.

A row’s ⋮ offers Edit, Log time, the task’s comments or agent notes, Make it a sub-project and Delete. Deleting a task with subtasks says the subtasks are deleted too.

Add a task under the list opens the add-task sheet with the cursor in the title. In it, Enter adds the task and closes, Shift+Enter adds it and starts the next one, and Esc closes the sheet.

Board, Timeline and Calendar

  • Board: a column per status (Waiting, Can be started, In progress, Done). Drag a card to another column to change its status. The In progress column is left out when the project’s in-progress step is off, unless a task is still in it.
  • Timeline: the tasks on a time chart, from the project’s schedule.
  • Calendar: the tasks on a month calendar.
The Board view of Website relaunch: task cards in Waiting, Can be started, In progress and Done columns, with Start, Allow start and Reopen buttons The Board view of Website relaunch: task cards in Waiting, Can be started, In progress and Done columns, with Start, Allow start and Reopen buttons

The same tasks on the Board, one column per status.

Logging time

Log time (on a task row, or for the whole project when Time logging on the project is on) asks How long, a Note and, when billable time is on, Billable. The time goes into the project’s work ledger and shows on the Hours tab.

Public submissions

With the public portal on, issues sent from the public board wait for review. Review submissions opens them: Accept adds one to the project, Reject “keeps a record and shows nobody.”

What it doesn’t do

  • Health is never computed: it’s only what someone set. It isn’t offered on a project without Start & finish.
  • Templates show the task list only, without the views strip.
  • A subtask can’t become a sub-project; move it to the top of the list first.